The Project

The administration and infrastructure rehabilitation of the project is planned for five phases, with the first phase starting in November 2018. The construction during Phase 1 is planned to be completed in one year, which provides the City a construction break for two years. Planning for Phase 2 starts in FY2021 and construction is planned for FY2022. This pattern repeats for the next three phases and should be complete in FY2033.

Project Timeline

Water & Sewer Line Maps

Please click on the maps to see the planned water/sewer line replacements for Phase 1 of this project. On the water map, the proposed lines are purple and the green lines represent infrastructure recently replaced. 

The sewer line map is busier due to the amount of work already done on the lines. The proposed lines for Phase 1 are shown in blue. 

Your Money At Work

FY 2021 Revenue Money Spent  Water Sewer
Oct - Dec $3,000,000