Contact Us

NB Weather

Search the Site

City Offices
1800 NASA Parkway
Nassau Bay, TX 77058
281.333.4211
How to get here

Building Permits

Permits may obtained Monday through Friday: 8:00 AM - 5:00 PM. In case of an EMERGENCY, please tell the Police Dispatcher at (281) 333-4211 and the Building Official will be called to assist.  The E-mail address is larry.boles@nassaubay.com

Building Department Functions

  • Plan Review & Approval
  • Trades Registrations
  • Building Permits Issue
  • Building Inspections
  • Flood Plain Administration
  • Code Enforcement
  • Signs Permit Issue Building Complaint

What You Need to Know


Permitting Procedure
The General Contractor or Builder will procure all permits for building in Nassau Bay by filling out the Permit Application Form.

For All New Construction
The Owner, Architect or General Contractor will have to submit to the Building Department the following documents for Plan Review and Approval:

  1. Residential - Two complete sets of blueprints and calculations.
  2. Commercial - Two complete sets of blueprints and calculations
    (Architectural, structural, electrical, plumbing and HVAC).  Foundation Plans and Framing Plans must have the seal of a structural engineer, registered in the State of Texas.
  3. Plot Plan or Site Plan, and Legal Description. 
  4. Site Survey, boundary and topographical, certified by an engineer or surveyor.
  5. Electrical Load Analysis and Plumbing Riser Diagram.
  6. Elevation Certificate, FEMA Form 81-31, Jul 00 .
  7. Copy of Water and Sewer Tap receipt.
  8. Approval by Home Owners Association, if applicable

For New Commercial Construction
In addition to the items listed for new construction, the following items will have to be submitted:

  1. Approval by the Planning Commission and, if required , by City Council.
  2. Approval by the  Fire Marshal, and, if required, by the  Harris County Health Department.
  3. For projects fronting on NASA Parkway, provide TxDOT Permits for driveways and drainage, if the site design changes from existing.
  4. ADA Letter of Review and Approval, if the project cost is $50,000 or more.
  5. After completion of project, "As Built" plans showing all site utilities, must be submitted to the Building Department before the Final Occupancy Inspection can be completed.

For Additions, Modifications or Repairs
For structural, plumbing, electrical, gas, or cooling/heating equipment work, a permit and specific inspections will be required.

The owner or contractor will have to submit at least a sketch of the work proposed, a copy of a current survey, a letter of Approval by the Homeowners Association, and a rough construction cost estimate, when applying for a building permit.

Swimming pools, including concrete work, electrical, gas and plumbing require permits and inspections. Foundation repairs and future re-adjustments also require permits and inspections.

Cosmetic changes, non-structural repairs, or fence replacements do not require a permit.

House or Building Moving
Any structure to be moved within or into Nassau Bay, if over 8 feet wide and/or over 30 feet long, does require a permit, and if necessary, coordination with the Police Department.

Building Demolition
All buildings to be demolished will have to be permitted for demolition.

Return to Top

Permit Requirements for Crafts and Trades
The General Contractor or Builder will be responsible for ensuring that the following crafts are properly licensed or registered and insured in Nassau Bay:

Electricians (All Master and Journeyman Electricians)

The following crafts must register their current State license and provide proof of proper insurance before a permit can be issued:

Plumbing Contractors
HVAC Contractors
Irrigation Contractors

No permit will be issued without the name of the company and the name of the Master appearing on the permit application form.

A Composite Building Permits will be issued in full only to the General Contractor.

Return to Top

Permit Fee Schedule
Effective January 1, 2002, the City of Nassau Bay, Texas shall apply the following value-based fees:

Composite Building Permit:
     Building Permit Fee 0.50% of total construction value
     Plan Check Fee 0.25% of total construction value
     Mechanical Permit Fee 0.11% of total construction value
     Electrical Permit Fee 0.13% of total construction value
     Plumbing Permit Fee 0.12% of total construction value
          Total 1.11%  
Stand-alone Permits:    
     Building Permit Fee 1.00% of total construction value
     Plan Check Fee 0.50% of total construction value
     The minimum Fee is $25.00.    
Mechanical Permit Fee 1.00% of mechanical work value
     Plan Check Fee 0.50% of mechanical work value
     The minimum Fee is $25.00.    
Electrical Permit Fee 1.00% of electrical work value
     Plan Check Fee 0.50% of electrical work value
     The minimum Fee is $25.00.    
Plumbing Permit Fee 1.00% of plumbing work value
     Plan Check Fee 0.50% of plumbing work value
     The minimum Fee is $25.00.    
Composite Swimming Pool Permit
     Pool Permit Fee 0.50% of total construction value
     Plan Check Fee 0.25% of total construction value
     Electrical Permit Fee 0.05% of total construction value
     Plumbing Permit Fee 0.10% of total construction value
Fire Alarm System Permit    
     Fire Alarm Permit Fee 1.00% of system value
     Plan Check Fee 0.50% of system value
     The minimum Fee is $50.00.    
Fire Sprinkler System Permit    
     Fire Sprinkler Permit Fee 0.75% of system value
     Plan Check Fee 0.25% of system value
     The minimum Fee is $50.00.    
Fumigation Permit    
     Fumigation Permit Fee 0.75% of job cost
     Plan Check Fee 0.25% of job cost
     The minimum Fee is $25.00.    
Contractor Registration Fees    
     Annual Fee $50.00  
     One Time Fee $25.00  
Reinspection Fee $35.00  

Approval by Council September 12, 2005. Posted September 16, 2005 4:50 P.M. Removed 10-6-05. Pat Jones, City Secretary.

Return to Top

Inspections

Types and Sequence of Inspections:

T-Pole:
Temporary electrical power during construction

Ground Plumbing / Water Line:
When all grass and weeds are cleared from the site and the pipes are ready to be back-filled.  The pipes must have a water test on them with 10 foot head pressure.
Water lines from the tap to the building only, with pressure gage (60 PSIG). 

Slab:
Moisture barrier sealed, tub buckets in place, mastic on pipes, cables or rebar set, wire mesh and anchor bolts in place prior to concrete being placed.  Stringline needs to be across forms to show intended thickness of concrete. Provide a FEMA elevation certificate, verified by a surveyor, with sections "C, D and E" completed, if in a flood zone.

Water / Sewer Lines:
Sewer pipes must have water in them with 10 foot head pressure.

Framing & Windstorm / Hurricane Reinforcement:
Structure framed and braced only, no decking or sheathing. Wind bracing and strapping needs to be completed.

Cover Up:
All wiring, plumbing and HVAC components roughed in;  doors and windows set, roofing complete, structure dried in.  The plumbing (water and sewer) must have water test, and the gas pipes must have an air test ready (20 PSIG or 12 inches of mercury). 

Brick Tie:
Building is weathered-in;  ties nailed 16 inch on center horizontally and vertically.

Final Gas / Final Electric:
All electrical work complete and trimmed, appliances hooked up prior to permanent power. Gas lines must have an air test on (3 PSIG or 6 inches of mercury).

Concrete Flatwork (Driveways, Sidewalks, Decks, etc.):
After forms and expansion joints are up, reinforcing indicated, before concrete is placed.

Pool Concrete:
After excavation, reinforcing needs to be in place, before concrete or gunite is placed. Note:  Pool excavation needs to remain clear of the building's foundation load bearing area, and the swimming pool water line has to be at least 5 feet from any property line.

Pool Plumbing and Electrical:
After plumbing is installed and connected, and grounding loop is attached to reinforcing steel, and before cover-up.

Pool Deck:
After forms and expansion joints are complete, and all in-deck electrical and plumbing is finished.

Final Pool:
After all pool construction and mechanical work is completed, and after pool fences and self-closing gates are installed.

Final Occupancy:
The structure must be completely finished and ready to be occupied. A plot plan, showing "as-built" site utilities must be completed for the Building Department's records.  Landscaping must be completed.

No occupancy is permitted until the final inspection has been done. Permanent address number  must be on structure.

Note that other agencies and departments will also have to conduct inspections.  The Building Department cannot schedule for any of these agencies.

Fire Marshal (281) 333-4211 Thomas J. Cones/Chris Shannahan
Water Utilities (281) 333-4211  
Line Repair (281) 333-4211  
Health Department (713) 475-5529 Kathy Perez
Texas Windstorm (281) 474-5025  

Return to Top

Applicable Codes

  1. City Council repealed the 1997 Standard Technical Codes and the 1997 Fire Prevention Codes, effective January 1, 2002.
  2. City Council adopted the 2006 International Technical Codes, specifically the
    • International Property Maintenance Code.
    • International Building Code.
    • International Energy Conservation Code.
    • International Residential Code.
    • International Plumbing Code.
    • International Mechanical Code.
    • International Fuel Gas Code.
    • International Fire Code.
    • Life-Safety Code, NFPA 101, and the 2005 National Electrical Code, NFPA 70.
  3. City Council affirmed the retention of the City's Flood Damage Prevention Ordinance, the Zoning Ordinance and the Sign Ordinance and any other standard that has been adopted by ordinance that is more restrictive than the above codes

Return to Top

Plats
All Plats will be reviewed and approved by the Planning Commission, and 8 copies will be needed for the approval process.  A digitized computer copy of the Plat is to be submitted to the Building Department with two signed mylar copies when a new Plat or a Replat is filed with the Harris County Clerk.

Return to Top

ADA (Americans with Disabilities Act)
All Non-Residential Projects that will cost in excess of $50,000 must be registered, reviewed and approved by an Independent Contract Provider, registered with the Texas Department of Licensing  and Regulation, Code Review and Inspections, Architectural Barriers.  Contact the State Office at (512) 463-3211, or E-mail at architecturalbarriers@license.state.tx.us .  Their web page is www.license.state.tx.us.

Return to Top

Asbestos Survey
As of September 1, 2001, state law requires that all demolition and renovation of public or commercial buildings perform an asbestos survey.  The survey determines the presence of asbestos and will alert the building owner about whether various asbestos laws apply.  The permit applicant must provide evidence of the survey acceptable to the municipality.  The following number is available for any questions regarding this issue 1-800-572-5548 or 512-834-6610.

Return to Top

Special Precautions Required
When using Chemical Lime (Type S Hydrated Lime) please note that OSHA requires special protective measures:

  1. Respiratory protection
  2. Venting
  3. Protective gloves
  4. Eye protection; access to potable water for rinsing dust from eyes
  5. Full clothing to cover arms and legs
  6. Keep away from acids and maleic anhydride

For sewer line repairs under buildings, a fungicide is required.  The application of Chemical Lime is acceptable if applied directly to the excavated surfaces (provided the 6 protective measures are observed), or the lime can be mixed with the select backfill prior to back-filling the excavation.

The Material Safety Data Sheet can be downloaded at http://msds.pdc.cornell.edu/msdssrchasp.

Return to Top

Windstorm/Hurricane Protection
The Building Department requires that any structure within the city limits of Nassau Bay will provide the following materials and methods of construction for windstorm / hurricane protection:

 

A. A continuous load path from anchor bolts in the slab, through the bottom pressure treated plate, through the studs, onto the top plates, and continuing through the rafters, ridges, and trusses should be provided with a metal strapping system in accordance with SSTD 10-90, September 1997 edition.

B. Anchor Bolts should be one-half inch (1/2") diameter by eight inches (8") in length.  "Mud grip" devices of galvanized construction are also acceptable.  Either system will be installed prior to inspection and must be set at four foot (4'-0") on center, with eight inches (8") separations at corners.

C. Wall tie devices will be of standard galvanized or electroplated materials, and installed on sixteen inch (16") centers, vertically and horizontally.

D. Corner sheathing shall be one-half inch (1/2") plywood or equivalent material, nailed on all corners where applicable.  They shall be flush nailed at six inch (6") intervals along the perimeter and eight (8") intervals in the field of the panel.

Note:
The City of Nassau Bay cannot recommend any one manufacturer of these devices over another.  The illustrations have been provided by the Simpson Strong-Tie Company and have been used with permission. The illustrations are for general guidance only.  The City does not hereby endorse the products shown.

There are many similar devices produced, each designed for a specific application.  The builder needs to select the devices which apply to his situations.



Return to Top

Last updated 2/19/2008

2008 © City of Nassau Bay